Millboard Jetty Structure & Subframe

Project Type

Photography

Date

April 2023

The Photos show the galvanised steel structural frame
In this project we used a galvanised steel C-section box frame as the structural beams set onto 4 concrete pad foundations. Once the steel was installed we set the pond base using wire reinforced concrete. The subframe used to carry the decking boards is the Duo-Span aluminium and composite joist system with galvanic brackets between the steel and aluminium components.
Plas-pro recycled plastic joists and supports are used for building the curved step and attaching the fascia.
Fascia and cladding of the jetty legs is facilitated